ASX ANNOUNCEMENT
15 December 2023
VIKING RECEIVES EXCELLENT FIRST RESULTS IN STAGE 2
METALLURGICAL TESTWORK
•
Viking Mines has engaged Bureau Veritas to undertake Stage 2 metallurgical
testwork on samples obtained from the recent 7,500m drilling campaign at the
Canegrass Battery Minerals Project.
•
29 samples from hole VCRC0026 have been submitted, with the main zone from the
Fold Nose Deposit being evaluated.1
•
The testwork objectives are to produce vanadium pentoxide (V2O5) flake, via a series
of processes to extract and purify vanadium from the ore samples.
•
Initial sighter testwork to produce a magnetic concentrate from a 43.5kg composite
sample has been completed to establish grind size and concentrate characteristics.
•
Excellent mass recoveries up to 54.6% have been achieved which importantly
demonstrate limited sensitivity to grind size.
•
Concentrate grades up to 1.41% V2O5 has been achieved with >58% Fe, which is in
line with the Company objective of ensuring a marketable iron ore concentrate is
maintained.
•
Testwork is progressing with further regrind and cleaning of the concentrate to be
completed ahead of roasting to produce end products including high purity V2O5
flake.
Viking Mines Limited (ASX: VKA) (“Viking” or “the Company”) is pleased to provide an
update on the ongoing progress at the Company’s flagship Canegrass Battery Minerals Project
(“the Project” or “Canegrass”), located in the Murchison Region of Western Australia.
The Company recently released an updated Mineral Resource Estimate (MRE) for the Project,
delivering 146Mt at 0.70% V2O5, 31.8% Fe & 6.6% TiO2 (>0.5% V2O5), with a high-grade
subset of 27.5Mt at 0.87% V2O5, 37.3% Fe and 8.0% TiO2 (>0.8% V2O5).2
Stage 2 metallurgical testwork has commenced on samples from the Project and has been
designed to demonstrate a pathway to final saleable products. Samples are composited ahead
of producing a concentrate before further processing to produce high purity V2O5 flake along
with other marketable products.
Commenting on the commencement of the Stage 2 metallurgical testwork, Viking Mines
Managing Director & CEO Julian Woodcock said:
“I’m pleased to announce the initiation of Stage 2 metallurgical testwork for the Canegrass
Battery Minerals Project, a critical next step forward towards producing a high-quality Vanadium
Pentoxide flake.
“The start of this next phase aims to build on the success of the previous sighter testwork
completed by the Company and represents our commitment to advancing the Project forward.
“The first results we have received as part of the Stage 2 testwork demonstrate the high quality
of the ore, with impressive results including mass recoveries up to 54.6%, Vanadium recoveries
1
2
ASX Announcement Viking Mines (ASX:VKA) 4 September 2023 – Viking Drills Massive Vanadium Zone with 42m a 0.74%V 2O5
ASX Announcement Viking Mines (ASX:VKA) 20 November 2023 – VKA Resource Update Delivers Over 100% Growth at Canegrass
ASX:VKA
vikingmines.com
15-17 Old Aberdeen Place
West Perth, WA, 6005
P +61 8 6245 0870
F +61 8 9322 5230
contact@vikingmines.com
1
up to 93.1% and the concentrate grading 1.4% V2O5. The results also demonstrate a low
sensitivity to grind size, further enhancing the potential of the Project.
“Viking are rapidly advancing this high-value Project, and when the testwork is complete we will
be able to determine the best pathway to extract value for the benefit of shareholders. I look
forward to sharing the progress and results with the market as we achieve key milestones.”
Stage 2 Metallurgical Testwork Programme
Bureau Veritas have been engaged to conduct stage two metallurgical testwork on 29 samples
collected from hole VCRC0026, which was completed as part of Vikings extensive 7,500m
exploration drill program.1
29 one metre samples were selected from the main intercept within hole VCRC0026 above a
0.5% V2O5 cut-off (Figure 1).
The Stage 2 testwork is a critical next step for the Company focusing on the optimisation of
processes to produce a bulk concentrate that can be refined to produce a Vanadium Pentoxide
(V2O5) flake.
The testwork is expected to be completed by late in the March Quarter 2024, with the
Company providing an update on milestones achieved throughout this period.
Figure 1; Cross section through hole VCRC0026 from the Fold Nose Deposit showing the samples selected for metallurgical testwork.
The intercept selected for testwork reports 29m at 0.80% V2O5, 36.6% Fe and 8.8% TiO2 from 138m. Values shown are for V2O5.
ASX:VKA | vikingmines.com
2
Figure 2; Map showing the Fold Nose Deposit and the location of VCRC0026 with photo of the samples collected for metallurgical
testwork. Note the dark black colouration of the samples selected for testwork which is a characteristic of the massive magnetite
mineralisation of the mineralised zone.
First results from Stage 2 testwork
A 43.5kg bulk composite sample was created by combining 1.5kg of material from each of the
29 samples provided to the laboratory.
5 x 150g splits of this bulk composite sample underwent grind establishment tests to
determine the optimum grind size. Samples were ground to different size fractions ranging
from 212 to 45µm (P98) and underwent subsequent Davis Tube Recovery (DTR) testing to
produce a magnetic concentrate (Figure 3).
Analysis of the magnetic concentrate and tail produced has determined the following key
characteristics with results presented on Table 1 and Table 2 below:
•
The ore has a low sensitivity to grind size to produce a quality concentrate.
•
Mass recovery remains high, ranging between 52.2% to 54.6%
•
Concentrate grade remains consistent for key target elements, ranging between;
• V2O5: 1.40% to 1.41%
• Fe:
58.0% to 58.6%
• TiO2:
11.2% to 11.7%
•
Combined silica and alumina levels are low (from 4.1% to 4.6%) but will require a further
regrind and cleaning stage to achieve target levels <4%.
•
Ni, Cu and Co report to the tail in the concentrate process, with recoveries up to 85.5%,
90.8% and 76.2% respectively. This provides the opportunity to recover these valuable
commodities by performing a standard sulphide floatation process on the tail.
ASX:VKA | vikingmines.com
3
Table 1; Magnetic concentrate results showing mass recoveries, grades and metal recoveries by size fraction.
Concentrate
Grades (%)
Grind
µm
Mass
Size µm passing Recovery
(P98)
P80
(%)
V2O5
Sample
Number
Recoveries to
Concetrate
Fe
TiO2
SiO2
Al2O3
P
V2O5
Fe
TiO2
MC-45Con
45
31
52.2%
1.41
58.3
11.2
1.86
2.75
0.002
91.9%
82.7%
76.3%
MC-75Con
75
43
53.1%
1.41
58.6
11.5
1.62
2.67
0.002
92.4%
83.6%
78.5%
MC-106Con
106
66
54.6%
1.41
58.4
11.5
1.59
2.68
0.002
93.1%
84.6%
79.7%
MC-150Con
150
97
52.8%
1.41
58.4
11.7
1.46
2.67
0.003
91.6%
82.8%
79.1%
MC-212Con
212
145
53.2%
1.40
58.0
11.7
1.66
2.81
0.002
92.8%
83.5%
80.0%
Table 2; Tail results showing mass recoveries, grades and metal recoveries by size fraction.
Sample
Number
MC-45Tail
Grind
µm
Mass
Size µm passing Recovery
(P98)
P80
(%)
Tail Grades (%)
Recoveries to
Concetrate
Ni
Cu
Co
Ni
Cu
Co
45
31
47.8%
0.08
0.12
0.029
81.3%
90.5%
75.3%
MC-75Tail
75
43
46.9%
0.08
0.11
0.027
81.5%
89.8%
75.3%
MC-106Tail
106
66
45.4%
0.07
0.10
0.025
85.5%
90.8%
76.2%
MC-150Tail
150
97
47.2%
0.07
0.09
0.024
80.5%
83.4%
69.6%
MC-212Tail
212
145
46.9%
0.06
0.09
0.023
77.7%
79.5%
69.1%
Figure 3; Photos showing A) Samples being prepared for filtration after DTR testwork completed, B) Eirez Davis Tube tester
setup for sighter DTR testing and C) Magnetic concentrate produced after filtration.
ASX:VKA | vikingmines.com
4
NEXT STEPS
Based on the results received, the Companies metallurgical consultants have determined the
next stage of the testwork as follows. This work has commenced, and the Company will provide
an update in the March Quarter 2024 as further results are received.
•
Grind 38kg of the bulk composite sample to P80 145µm.
•
Perform Bulk Rougher Medium Intensity Magnetic Separation (MIMS) with P80 145 µm
(Grind P98 212 µm), 3000 gauss, 20% solids.
•
Regrind the Con from the Bulk Rougher MIMS to P80 45 µm and 75 µm.
•
Perform sighter DTR II on P80 45 µm and 75 µm. These results will be analysed to determine
regrind size after Bulk Rougher MIMS.
END
This announcement has been authorised for release by the Board of the Company.
Julian Woodcock
Managing Director and CEO
Viking Mines Limited
For further information, please contact:
Viking Mines Limited
Sarah Wilson - Company Secretary
+61 8 6245 0870
Forward-Looking Statements
This document may include forward-looking statements. Forward-looking statements include, but are not limited to, statements concerning Viking
Mines Limited’s planned exploration programme and other statements that are not historical facts. When used in this document, the words such as
"could," "plan," "estimate," "expect," "intend," "may”, "potential," "should," and similar expressions are forward-looking statements. Although Viking
Mines Limited believes that its expectations reflected in these forward-looking statements are reasonable, such statements involve risks and
uncertainties and no assurance can be given that actual results will be consistent with these forward-looking statements.
Competent Persons Statement – Metallurgical Results
The information contained in this report, relating to metallurgical results, is based on, and fairly and accurately represent the information and
supporting documentation prepared by Mr Damian Connelly. Mr Connelly is a full-time employee of METS Engineering who are a Contractor to
Viking Mines Ltd, and a Fellow of The Australasian Institute of Mining and Metallurgy. Mr Connelly has sufficient experience which is relevant to the
style of mineralisation and type of deposit under consideration, and to the activity being undertaken to qualify as a Competent Person as defined in
the 2012 Edition of the Australasian Code for Reporting of Exploration Results, Exploration Targets, Mineral Resources and Ore Reserves. Mr Connelly
consents to the inclusion in the report of the matters based on the results in the form and context in which they appear.
Competent Persons Statement – Exploration Results
Information in this release that relates to Exploration Results is based on information compiled by Mr Julian Woodcock, who is a Member and of the
Australian Institute of Mining and Metallurgy (MAusIMM(CP) – 305446). Mr Woodcock is a full-time employee of Viking Mines Ltd. Mr Woodcock has
sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity being undertaken to
qualify as a Competent Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and
Ore Reserves’. Mr Woodcock consents to the disclosure of the information in this report in the form and context in which it appears.
Competent Persons Statement – Mineral Resources
The information in this announcement that relates to the Mineral Resource estimate is derived from information compiled by Mr Dean O’Keefe, a
Fellow of the Australasian Institute of Mining and Metallurgy (AusIMM, #112948), and Competent Person for this style of mineralisation. Mr O’Keefe
is a consultant to Viking Mines Limited, and is employed by MEC Mining, an independent mining and exploration consultancy. Mr O’Keefe has
sufficient experience relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to
qualify as Competent Person as defined in the 2012 edition of the Australasian Code for the Reporting of Exploration Results, Mineral Resources, and
Ore Reserves (JORC Code). The Company confirms that the form and context in which the results are presented and all material assumptions and
technical parameters underpinning the estimates in the original market announcement continue to apply and have not materially changed from the
original announcement and that the form and context in which the Competent Person’s findings are presented have not been materially modified
from the original announcement on 20 November 2023.
ASX:VKA | vikingmines.com
5
CANEGRASS BATTERY MINERALS PROJECT
The Canegrass Battery Minerals Project is located in the Murchison region, 620km north-east
of Perth, Western Australia. It is accessed via sealed roads from the nearby township of Mt
Magnet to within 22km of the existing Resources. The Project benefits from a large
undeveloped Inferred Vanadium Resource hosted in vanadiferous titanomagnetite (VTM)
Mineralisation as part of the Windimurra Layered Igneous Complex.
The Project benefits from ~95km2 of exploration tenements with very limited follow up
exploration targeting the growth potential of the vanadium pentoxide (V2O5) Resources in the
+10 years since the Resource was first calculated and prior to Vikings involvement.
Viking has completed substantial exploration activity since acquiring the Project which has
culminated in a substantial Mineral Resource Estimate upgrade, doubling the amount of
contained V2O5. The Company is progressing with further metallurgical testwork and studies
with the objective of completing a scoping study in 2024 to determine the potential economics
of the Project.
JORC (2012) MINERAL RESOURCE
The Canegrass Mineral Resource has been calculated across three separate areas called the
Fold Nose, Kinks and Kinks South deposits. The Resource has subsequently been reported
above a cut-off grade of 0.5% V2O5 and above the 210 RL (equivalent to a maximum depth of
~250m)(refer to ASX Announcement on 20 November 2023).
Canegrass Project Vanadium Mineral Resource estimate, 0.5% V 2O5 cut-off grade, >210m RL.
Target Commodities
Deleterious Elements
JORC (2012) Cut-Off Tonnage
Ni
Co Al2O3 SiO2
P
V2O5 Fe TiO2 Cu
Classification V2O5%
(Mt)
%
%
%
%
%
%
%
%
%
VKA 2023 Model
Inferred
>0.5
146
0.70 31.8 6.6 0.066 0.062 0.016 11.7 21.7 0.005
MRE
LOI
%
1.7
VIKING MINES FARM-IN AGREEMENT
Viking, via its wholly owned subsidiary, Viking Critical Minerals Pty Ltd, commenced with a
Farm-In arrangement with Red Hawk Mining Ltd (formerly Flinders Mines Ltd) (ASX:RHK) on 28
November 2022 to acquire an equity interest in the Canegrass Battery Minerals Project.
Through the terms of the Farm-In, Viking can acquire up to 99% of the Project through
completion of 4 stages via a combination of exploration expenditure of $4M and staged
payments totalling $1.25M over a maximum period of 54 months. As of August 2023, Viking
has acquired 25% of the Project through the FIA.
If Viking complete the Farm-In to 99% equity interest, Red Hawk may offer to sell to Viking the
remaining 1% of the Project for future production and milestone related payments totalling
$850,000. If Red Hawk Mining do not offer to sell within a prescribed timeframe their right
lapses, they must offer Viking the right (but not the obligation) to buy the remaining 1% for the
same terms.
The Project has a legacy 2% Net Smelter Royalty over the project from when Red Hawk Mining
acquired it from Maximus Resources in 2009.
ASX:VKA | vikingmines.com
6
VANADIUM REDOX FLOW BATTERIES – GREEN ENERGY FUTURE
Viking Mines recognise the significant importance of Vanadium in decarbonisation through the
growth of the Vanadium Redox Flow Battery (“VRFB’s”) sector.
VRFB’s are a developing market as an alternate solution to lithium-ion (“Li-ion”) in specific large
energy storage applications. Guidehouse Insights Market Intelligence White Paperi published
in 2Q 2022 forecasts the VRFB sector to grow >900% by 2031 through the installation of large,
fixed storage facilities (Figure 44).
Figure 4; Forecast growth of the VRFB Sector through to 2031 (source – Guidehouse Insightsi)
The reason for this forecast growth is that VRFB’s have unique qualities and advantages over
Li-ion in the large energy storage sector to complement renewable energy sources to store the
energy produced. They are durable, maintain a long lifespan with near unlimited
charge/discharge cycles, have low operating costs, safe operation (no fire risk) and have a low
environmental impact in both manufacturing and recycling. The Vanadium electrolyte used in
these batteries is fully recyclable at the end of the battery’s life.
Importantly, and unlike Li-ion, the battery storage capacity is only limited by the size of the
electrolyte storage tanks. This means that with a VRFB installation, increasing energy storage
capacity is only a matter of adding in additional electrolyte (via the installation of additional
electrolyte storage tanks) without needing to expand the core system components. Increasing
the energy storage directly reduces the levelized cost per kWh over the installation’s lifetime.
This is not an option with Li-ion batteries.
It is for these reasons that VRFB’s are an ideal fit for many storage applications requiring longer
duration discharge and more than 20 years of operation with minimal maintenance.
i) Guidehouse Insights White Paper Vanadium redox Flow Batteries Identifying Market Opportunities and Enablers Published 2Q 2022
https://vanitec.org/images/uploads/Guidehouse_Insights-Vanadium_Redox_Flow_Batteries.pdf
ASX:VKA | vikingmines.com
7
APPENDIX 1 – DETAILED METALLURGICAL RESULTS TABLE
Concentrate and tail analysis results and recoveries
Sample
Number
MC-45Con
Concentrate
Grades (%)
Grind
µm
Mass
Size µm passing Recovery
(P98)
P80
(%)
V2O5
Recoveries to
Concetrate
Fe
TiO2
SiO2
Al2O3
P
Ni
Cu
Co
V2O5
Fe
TiO2
SiO2
Al2O3
P
Ni
Cu
Co
45
31
52.2%
1.41
58.3
11.2
1.86
2.75
0.002
0.025
0.022
0.012
91.9%
82.7%
76.3%
5.3%
16.7%
43.9%
25.7%
17.3%
31.2%
MC-75Con
75
43
53.1%
1.41
58.6
11.5
1.62
2.67
0.002
0.026
0.025
0.012
92.4%
83.6%
78.5%
4.7%
16.6%
44.7%
27.9%
20.6%
33.4%
MC-106Con
106
66
54.6%
1.41
58.4
11.5
1.59
2.68
0.002
0.024
0.027
0.012
93.1%
84.6%
79.7%
4.9%
17.6%
46.2%
28.9%
24.5%
36.6%
MC-150Con
150
97
52.8%
1.41
58.4
11.7
1.46
2.67
0.003
0.024
0.028
0.013
91.6%
82.8%
79.1%
4.2%
16.6%
61.0%
28.0%
25.4%
37.7%
MC-212Con
212
145
53.2%
1.40
58.0
11.7
1.66
2.81
0.002
0.026
0.032
0.013
92.8%
83.5%
80.0%
4.8%
17.5%
44.8%
31.5%
29.9%
39.1%
Sample
Number
MC-45Tail
Tail
Grades (%)
Grind
µm
Mass
Size µm passing Recovery
(P98)
P80
(%)
V2O5
Recoveries to
Tail
Fe
TiO2
SiO2
Al2O3
P
Ni
Cu
Co
V2O5
Fe
TiO2
SiO2
Al2O3
P
Ni
Cu
Co
36.19
15.05
0.003
0.079
0.115
0.029
8.1%
17.3%
23.7%
94.7%
83.3%
56.1%
74.3%
82.7%
68.8%
45
31
47.8%
0.14
13.4
3.81
MC-75Tail
75
43
46.9%
0.13
13.0
3.56
37
15.22
0.003
0.076
0.109
0.027
7.6%
16.4%
21.5%
95.3%
83.4%
55.3%
72.1%
79.4%
66.6%
MC-106Tail
106
66
45.4%
0.13
12.8
3.52
36.77
15.07
0.003
0.071
0.100
0.025
6.9%
15.4%
20.3%
95.1%
82.4%
53.8%
71.1%
75.5%
63.4%
MC-150Tail
150
97
47.2%
0.15
13.6
3.45
37.1
14.96
0.002
0.069
0.092
0.024
8.4%
17.2%
20.9%
95.8%
83.4%
39.0%
72.0%
74.6%
62.3%
MC-212Tail
212
145
46.9%
0.12
13.0
3.31
37.33
15.01
0.003
0.064
0.085
0.023
7.2%
16.5%
20.0%
95.2%
82.5%
55.2%
68.5%
70.1%
60.9%
Grind size distribution results
Sample
MC-45
Mass to 20um screen 122.41
+20um
-20um
212
150
106
41.34
77.04
75
MC-75 MC-106 MC-150 MC-212
122.98
121.45
124.7
127.05
60.42
57.34
67.22
50.6
82.99
38.31
0.6
0.8
17.6
95.64
27.82
0.2
22.7
18.2
3.6
15.8
19.1
16.6
13.6
53
2.2
8.1
16.9
15.6
45
38
20
-20
-20 wet
2.7
7.8
26.4
1.2
77.04
8.1
6.6
22.4
1.4
57.34
7.4
5.8
18.9
1.6
50.6
6.7
5.2
15.8
1.3
38.31
ASX:VKA | vikingmines.com
9.7
13.5
1.5
27.82
Cumulative % Passing
Sample MC-45
MC-75 MC-106 MC-150 MC-212
212
150
106
75
53
100.0% 100.0% 100.0% 100.0%
100.0% 100.0% 100.0% 99.3%
100.0% 100.0% 99.5% 84.7%
100.0% 96.7% 86.1% 68.9%
98.1% 89.1% 71.7% 55.9%
99.8%
81.5%
66.8%
53.4%
42.4%
45
95.8%
81.6%
65.4%
50.3%
42.4%
38
89.2%
75.5%
60.5%
46.0%
34.6%
20
-20
66.7%
65.7%
54.6%
53.3%
44.4%
43.0%
32.9%
31.8%
23.7%
22.5%
P80 µm
30.7
43.2
65.7
96.8
145.5
8
APPENDIX 2 – JORC CODE, 2012 EDITION – TABLE 1
JORC Table 1, Section 1 – Sampling Techniques and Data
JORC Code explanation
Criteria
Sampling
techniques
Drilling
techniques
Nature and quality of sampling (e.g. cut channels, random chips, or specific specialised industry standard
measurement tools appropriate to the minerals under investigation, such as downhole gamma sondes, or
handheld XRF instruments, etc.). These examples should not be taken as limiting the broad meaning of
sampling.
Include reference to measures taken to ensure sample representivity and the appropriate calibration of any
measurement tools or systems used.
Aspects of the determination of mineralisation that are Material to the Public Report. In cases where ‘industry
standard’ work has been done this would be relatively simple (e.g. ‘reverse circulation drilling was used to obtain
1 m samples from which 3 kg was pulverised to produce a 30 g charge for fire assay’). In other cases more
explanation may be required, such as where there is coarse gold that has inherent sampling problems. Unusual
commodities or mineralisation types (e.g. submarine nodules) may warrant disclosure of detailed information
Drill type (e.g. core, reverse circulation, open-hole hammer, rotary air blast, auger, Bangka, sonic, etc.) and
details (e.g. core diameter, triple or standard tube, depth of diamond tails, face-sampling bit or other type,
whether core is oriented and if so, by what method, etc.).
Method of recording and assessing core and chip sample recoveries and results assessed.
Drill sample
recovery
Measures taken to maximise sample recovery and ensure representative nature of the samples.
Whether a relationship exists between sample recovery and grade and whether sample bias may have occurred
due to preferential loss/gain of fine/coarse material.
Whether core and chip samples have been geologically and geotechnically logged to a level of detail to support
appropriate Mineral Resource estimation, mining studies and metallurgical studies.
Logging
Whether logging is qualitative or quantitative in nature. Core (or costean, channel, etc.) photography.
The total length and percentage of the relevant intersections logged.
ASX:VKA | vikingmines.com
Commentary
RC drilling collected samples during the drilling process using industry
standard techniques including face sampling drill bit and cone splitter.
Chip samples are collected from the drill cuttings and sieved and put
into chip trays for geological logging.
Cone splitter subsamples the interval drilled and ensures that the
sample collected is representative of the interval drilled.
Reverse circulation drilling was used to obtain 1m samples which were
collected from the cone splitter. Samples have been composited in
some cases to either 2 or 4m composites by scooping from the calico
bag collected from the cone splitter at the rig. Samples were
dispatched to ALS laboratories in Perth for analysis by a XRF fused bead
analysis.
Reverse circulation drilling using a 5 ½ inch bit and a face sampling
hammer.
Recovery of sample is recorded by the field assistant when sampling and
noted as either Good, Fair or Poor. Of the samples collected from the
drilling programme, very few samples reported fair or poor recovery and
no issues were identified with sample recovery for any samples related
to the mineralised horizons.
Drilling recovery is assessed by observing sample size. Samples are
collected from the cyclone using a cone splitter and monitored for size
to determine that they are representative.
No relationship has been identified between sample recovery and
grade. This is reflected by all samples collected having a good recovery.
Further, due to the nature of the mineralisation under investigation
and the relatively high values obtained, the impact of fines is not
considered to be of significance.
All chip samples have been geologically logged to a sufficient level to
support any future mineral resource estimation, mining studies and
metallurgical studies. All chip samples are retained at the Company
offices and are available for further inspection when undertaking this
future work.
Logging of samples is qualitative in nature. Chip photos are taken of the
chip trays. All the drill spoils at the drill site are photographed to retain
a record of the colour variation within the hole.
All metres drilled have been geologically logged.
9
JORC Code explanation
Criteria
If core, whether cut or sawn and whether quarter, half or all core taken.
If non-core, whether riffled, tube sampled, rotary split, etc. and whether sampled wet or dry.
For all sample types, the nature, quality and appropriateness of the sample preparation technique.
Subsampling
techniques and
sample
preparation
Quality control procedures adopted for all subsampling stages to maximise representivity of samples.
Measures taken to ensure that the sampling is representative of the in-situ material collected, including for
instance results for field duplicate/second-half sampling.
ASX:VKA | vikingmines.com
Commentary
Not applicable.
Samples were collected from the cyclone using a cone splitter for each
metre drilled in to 2 calico bags. When composite samples were
collected, a scoop is used to collect equal amounts from each metre
interval used to make the composite sample. Dry samples are
collected.
For drill samples, The sample preparation of the RC samples follows
industry best practice, involving oven drying, pulverising, to produce a
homogenous sub sample for analysis. All samples were pulverised to a
nominal 85% passing 75-micron sizing and sub sampled for assaying
and LOI determination tests. The sample preparation techniques are of
industry standard and are appropriate for the sample types and
proposed assaying methods.
For metallurgical samples, calico bags from each of the 1m samples
under investigation were collected from the field and submitted to
Bureau Veritas. A master composite has been created using 1.5kg of
sample from each of the samples provided. 5x 150g splits of this
sample have undergone grind size and residence time testwork to
determine appropriate grind size for next stages of testwork. Analysis
results of the composite compare closely to that of the mathematically
composited interval from the drilling analysis results, supporting the
appropriateness of the techniques used to produce the composite
sample. The competent person has determined that the sample
preparation technique is appropriate for the sample types.
For drill samples, standard, blank and duplicate samples are inserted in
the sampling sequence at a rate of 1 per 20 samples (standard or blank).
This is in addition to the laboratory QAQC procedures adopted. The
quality control procedures to ensure and maximise sample
representivity are deemed appropriate.
For metallurgical testwork, Laboratory standards were used in the
analysis of the composite sample and DTR testwork samples. No issues
have been reported by the laboratory.
Drilling was conducted using a 5 ½ inch hammer to collect 1m samples.
As the style of mineralisation is massive to disseminated with results
for V2O5 being measured in %, the samples collected are deemed
representative. To monitor this, duplicate samples are collected from
the cyclone at a frequency rate of approximately 1 per 40 samples
collected (~2.5%).Samples are selected from expected mineralised
intervals to provide meaningful data to compare the original vs the
duplicate. Duplicate samples show a good correlation against the
10
JORC Code explanation
Criteria
Whether sample sizes are appropriate to the grain size of the material being sampled.
The nature, quality and appropriateness of the assaying and laboratory procedures used and whether the
technique is considered partial or total.
Quality of assay
data and
laboratory tests
For geophysical tools, spectrometers, handheld XRF instruments, etc., the parameters used in determining the
analysis including instrument make and model, reading times, calibrations factors applied and their derivation,
etc.
Nature of quality control procedures adopted (e.g. standards, blanks, duplicates, external laboratory checks) and
whether acceptable levels of accuracy (i.e. lack of bias) and precision have been established.
ASX:VKA | vikingmines.com
Commentary
original sample collected indicating that sampling is representative of
the in-situ material collected.
No duplicate samples have been prepared as part of the metallurgical
testwork programme.
The Competent Person considers the current methods and processes
described as appropriate for this style of mineralisation.
Grind size establishment testwork for the metallurgical testwork
programme showed variable grind sizes but with no apparent influence
on recovery or grade.
The nature and style of the mineralisation is relatively homogenous
and as such the sample sizes collected are appropriate to the grain size
of the material being sampled.
For drill samples, Samples were sent to ALS laboratories in Perth for
preparation and analysis. Samples were riffle split to 250g then
pulverised to a nominal 85% passing 75 microns. The Vanadium
samples underwent analysis by ME-GRA5 (H20 LOI) and MEX-XRF21u
(iron ore by XRF fusion).
For metallurgical samples, samples were analysed by Bureau Veritas in
Perth. Samples were ground to a target size of P80 75 micron grind
with actual grind results reported in appendix 1. XRF-202 method was
used by Bureau Veritas to analyse the samples.
The analysis methods chosen are considered appropriate for the style
of mineralisation.
Field tools were used to assist in identification of the VTM horizon for
sampling. A KT-10 magnetic susceptibility meter has bee