STOCKPILE AND TAILINGS EVALUATION UNDERWAY AT LINKA TUNGSTEN
Released
Released
Announcement PDF
ASX ANNOUNCEMENT
14 April 2026
ASX:VKA
vikingmines.com
15-17 Old Aberdeen Place
West Perth, WA, 6005
P +61 8 6245 0870
F +61 8 9322 5230
contact@vikingmines.com
1
STOCKPILE AND TAILINGS EVALUATION UNDERWAY
AT LINKA TUNGSTEN PROJECT
• Field team has mobilised to the Linka Project to execute a field programme designed to
evaluate the historical tailings dam and ore stockpiles.
• Systematic sampling underway to determine both grade and volume of the historical
tailings to assess potential for reprocessing as a low cost, supplemental plant feedstock.
• Sampling of historical ore stockpiles aims to validate high-grade potential, building on
previous composite result1
of 0.8% WO3 to evaluate immediate commercial value.
• Advanced metallurgical testing continues following recent success2
achieving a 53-fold
upgrade to produce a premium 63.6% WO3 concentrate from primary mineralisation.
• Additional metallurgical sample collection for comminution testwork and to provide
definitive energy and OPEX data to support the ongoing conceptual processing study.
• Initial field investigations are ground-truthing the 3D geological model and geophysical
targets, including an 820m mineralised corridor and 800m extension under cover.
• Phase 2 activity scheduled for late April will include detailed mapping and trench
sampling to finalise layouts for the maiden June Quarter drilling campaign.
• Global tungsten prices continue to rise and exceed all-time highs with APT at
US$3,185/mtu3
.
1
ASX Announcement 14 January 2026 – High Grade Assays up to 1.3% WO3 from Linka Tungsten Project
2
ASX Announcement 31t
March 2026 – Vikings Linka project achieves 63.6% WO3 Concentrate
3
Source: Shanghai Metals Markets 13th
April 2026 https://www.metal.com/tungsten - CIF Rotterdam 88.5% APT US$/mtu (metric tonne unit – 10kg)
Figure 1; Photo of the Linka Tungsten Project showing historic mines, mill site, stockpiles and tailings dam.
2
ASX:VKA | vikingmines.com
Viking Mines Limited (ASX: VKA; OTC:VKALF) ("Viking" or "the Company") is pleased to
announce that a campaign of field operations has now commenced at the Linka Tungsten Project
in Nevada, USA. A field team has mobilised to site this weekend to execute a multi-faceted
programme designed to quantify the historical ore stockpiles and tailings dam and prepare the
project for subsurface exploration.
Viking Mines Managing Director & CEO Julian Woodcock said:
“Viking has commenced a period of high activity, transitioning from analysis into active project
development. Our workstreams target a rapid, low-CAPEX pathway to production. With tungsten
at 90-year highs, the strategic value of our Nevada assets is clear, and we look forward to providing
updates as milestones are achieved.”
SURFACE ASSET EVALUATION
The Company commenced a field programme to evaluate the historical ore stockpiles and tailings
dam, representing a significant near "zero-mining-cost" opportunity to identify short-term
commercialisation pathways that bypass traditional extraction costs.
The technical workstream incorporates grid-sampling the historical tails dam, collecting
approximately 52 samples (Figure 2) to determine both WO3 grade and tailings dam thickness.
This dataset will enable the Company to calculate the volume and grade of the tailings dam to
determine inherent value and subsequently commence with metallurgical testwork to evaluate
the economic viability of tailings reprocessing. If recoverability is confirmed, this material could
serve as a low-cost supplemental feed for a future "Rapid-Start" modular plant.
Simultaneously, teams are sampling the historical stockpiles to confirm grade consistency,
following the results from LKMET0001 (97.4kg composite sample returning 0.8% WO3)1
. A
volumetric estimate will also be conducted to determine stockpile tonnage. The strategic intent
for the stockpile is to assess viability for early processing via toll treatment or pilot plant to
produce concentrate samples for potential offtake partners and finalising negotiations for early-
stage cash flow.
ADVANCING METALLURGY
To support the ongoing Processing Concept Study4
being conducted by Mineral Technologies,
the Company has initiated the collection of additional metallurgical samples for a suite of
comminution tests. This testwork phase is essential for defining the operational expenditure
(OPEX) profile of the project and ensuring modular plant scalability.
The testing suite includes:
• Crushing Work Index (CWi) and Abrasion Index (Ai): To determine the power requirements
and wear-resistance needed for primary and secondary crushing stages.
• SMC (SAG Mill Comminution): To establish the rock-breakage parameters required for
Autogenous or Semi-Autogenous mill sizing, providing data on rock hardness and impact
resistance.
• Bond Rod & Ball Mill Work Indices (BRMWI/BBMWI): To calculate the precise kilowatt-
hours per tonne required to grind the ore to its optimal liberation size for gravity separation.
4
ASX Announcement 17 March 2026 – Viking Engages Mineral Technologies for Linka Tungsten
3
ASX:VKA | vikingmines.com
Figure 2; Map showing the Linka Tungsten Project historical tailings dam and planned sampling locations.
4
ASX:VKA | vikingmines.com
Figure 3; Photos showing; A: Sample collection, B: riffle splitting sample, C: bagging of sample & D: preparing sample
bags and data recording.
5
ASX:VKA | vikingmines.com
GEOLOGY & PHASE 2 ROADMAP
Field activity also includes initial ground-truthing high-priority targets identified via the 3D
geological model and recent geophysics. This involves validating the interpretation of the 820m
sub-cropping corridor, specifically investigating the 800m extension identified beneath
volcanic cover to the southwest. This ground-truthing confirms the presence of garnetite skarn
signatures ahead of subsurface testing.
Following the completion of Phase 1 activity, the Company will transition into Phase 2 later this
month. This next stage of field work will include:
• Detailed follow-up mapping: Expanding on current observations to refine structural
controls.
• Trench and outcrop sampling: Providing direct access to mineralised units for grade
validation.
• Drill site investigation and hole layouts: Finalising precise collar locations for the upcoming
programme.
• Logistics preparations for drilling: Ensuring site infrastructure is ready for the maiden June
Quarter drilling campaign.
ONGOING WORK AND NEXT STEPS
Viking continues to fast track the Linka Tungsten Project through multiple workstreams and are
targeting drilling commencing in the June quarter. Immediate near term activity includes:
• Completion of field activity to sample the historical tailings dam and stockpiles.
• Commencement or phase 2 field programme late April involving surface geological mapping
to assess targets generated from gravity and magnetic geophysics surveys and historical
trench sampling.
• Completion and reporting of the 3D geological model used to plan drilling and for potential
use in determining a JORC (2012) exploration target.
• Lodging a Notice of Intent for maiden drilling programme at the Linka Project with the Bureau
of Land Management.
• Ongoing metallurgical testwork, with cleaner flotation testwork results expected in April.
END
This announcement has been authorised for release by the Board of the Company.
Julian Woodcock
Managing Director and CEO
Viking Mines Limited
For further information, please contact:
Michaela Stanton-Cook - Company Secretary
Viking Mines Limited
+61 8 6245 0870
Forward-Looking Statements
This document may include forward-looking statements. Forward-looking statements include, but are not limited to, statements concerning Viking Mines
Limited’s planned exploration programme and other statements that are not historical facts. When used in this document, the words such as "could,"
"plan," "estimate," "expect," "intend," "may”, "potential," "should," and similar expressions are forward-looking statements. Although Viking Mines Limited
believes that its expectations reflected in these forward-looking statements are reasonable, such statements involve risks and uncertainties and no
assurance can be given that actual results will be consistent with these forward-looking statements.
Share your feedback
Discover