Quarterly Report for the period ended 31 December 2023
Released
Released
Announcement PDF
ASX ANNOUNCEMENT
22 January 2024
QUARTERLY REPORT FOR THE PERIOD ENDED
31 DECEMBER 2023
Canegrass Battery Minerals Project
•
Viking Mines completed an updated JORC (2012) Mineral Resource Estimate (MRE)
for the Canegrass Battery Minerals Project (the Project), representing a 103%
increase, now containing >2.2 Billion Pounds of the Critical mineral Vanadium
Pentoxide (V2O5).1
•
Total Inferred MRE for the Project: 146Mt at 0.70% V2O5, 31.8% Fe & 6.6% TiO2
(>0.5% V2O5 cut-off).
•
High-grade subset of the MRE: 27.5Mt at 0.87% V2O5, 37.3% Fe & 8.0% TiO2 (>0.8%
V2O5 cut-off).
•
Viking Mines engaged Bureau Veritas to undertake Stage 2 metallurgical testwork to
produce V2O5 flake from samples obtained from RC drilling completed mid 2023.
•
Excellent mass recoveries up to 54.6% achieved which importantly demonstrate
limited sensitivity to grind size. 2
•
Concentrate grades achieved up to 1.41% V2O5 and >58% Fe, which is in line with the
Company target ensuring a marketable iron ore concentrate is maintained.
First Hit Lithium and Gold Project
•
Viking Mines purchases strategic tenement on the Mt Ida Fault zone, bringing the
total granted land package in this prospective Lithium district to ~291km.2 & 3
•
Mapped pegmatites occur throughout the new tenement, with historical rock chip
sampling confirming highly anomalous rare element pegmatite results including
Lithium up to 400ppm and Rubidium values up to 3,000ppm.
•
Auger drilling programme completed and collected 1,220 samples over a 26km
strike length of the Ida Fault and tests >55km2 of highly prospective tenure.4
Corporate
•
Strong cash position of $5.1M as of 31 December 2023.
•
Appointment of Joint Company Secretary Ms Michaela Stanton-Cook.5
•
Mr Bevan Tarratt was appointed as Non-Executive Director of the Company.6
Viking Mines Limited (ASX:VKA) (“Viking” or “the Company”) is pleased to present its
quarterly activities report for the period ended 31 December 2023 (“December quarter”). The
Company’s focus during the reporting period was advancing exploration programmes at the
Canegrass Battery Metals Project in Western Australia and a maiden Lithium focussed auger
drilling programme at the First Hit Project.
Viking Mines (ASX:VKA) ASX Announcement 20 November 2023 – VKA Resource Update Delivers Over 100% Growth at Canegrass
Viking Mines (ASX:VKA) ASX Announcement 15 December 2023 – Viking Receives Excellent Met Testwork Results at 1.4% V 2O5
3
Viking Mines (ASX:VKA) ASX Announcement 27 November 2023 VKA Grows Tenure & Starts Lithium Exploration at First Hit
4
Viking Mines (ASX:VKA) ASX Announcement 11 December 2023 – VKA Completes Lithium Focussed Auger Drilling at First Hit
5
Viking Mines (ASX:VKA) ASX Announcement 8 December 2023 – Appointment of Company Secretary
6
Viking Mines (ASX:VKA) ASX Announcement 3 October 2023 – Viking Appoints Non-Executive Director to the Board
1
2
ASX:VKA
vikingmines.com
15-17 Old Aberdeen Place
West Perth, WA, 6005
P +61 8 6245 0870
F +61 8 9322 5230
contact@vikingmines.com
1
WESTERN AUSTRALIA
CANEGRASS BATTERY MINERALS PROJECT
Updated Mineral Resource Estimate
During the reporting period, the Company successfully updated the MRE for the Canegrass
Project, with a 103% increase in the contained V2O5 to 2.2 Billion Pounds within the total MRE
(>0.5% V2O5) of 146Mt at 0.70% V2O5, 31.8% Fe & 6.6% TiO2. Significantly, a high-grade
subset of the MRE contains 27.5Mt at 0.87% V2O5, providing the basis to move forward and
commence a Scoping Study on the Project.
Figure 1 – Map of the Canegrass Project showing the JORC (2012) MRE for each of the deposit areas and the total
combined estimate. Note all Resources are Inferred category reported above a 0.5% V2O5 cut-off. Totals may vary
due to rounding
ASX:VKA | vikingmines.com
2
In November 2023. industry consultants, MEC Mining, completed the MRE update for the
Canegrass Project. The MRE update is the product of the extensive exploration campaign
undertaken by Viking since announcing the acquisition of the project in November 2022.
The tonnage has increased substantially, with improvements in grade for all the target
commodities. Further, the grade of the deleterious elements has decreased, which results in a
higher quality ore more amenable to processing to produce a magnetic concentrate.
Table 1 – 2023 Canegrass Project MRE update and comparison to 2017 model showing substantial growth in tonnes
and grade of the primary commodities (reported above a 0.5% V 2O5 cut-off). Note, Cu, Ni & Co were not estimated
for the Project in 2017.7
Table 2 – 2023 Canegrass Project MRE high-grade subset >0.8% V2O5 cut-off as a part of the total Resource.
Most significantly is a high-grade subset of the MRE when reported above the higher cut-off of
0.8% V2O5. This cut-off has been selected as it represents the change from disseminated
magnetite in gabbro to massive magnetite bands seen in the drilling data and forms
continuous zones which the Company believe could be amenable to mining.
This high-grade subset of the MRE will form the basis for Viking’s future work to assess the
economic viability of the Project and aligns with the Company’s aspirations to become a 1520 year mine life operator processing 1.5-2.0Mtpa
Growth Potential
With the extensive drilling completed by the Company and the completion of the MRE,
opportunities for further growth have been identified at each of the three deposit areas. This
provides further upside opportunity to both increase the tonnes and grade of the high-grade
subset of the total MRE.
With further drilling in these areas, the Company remains optimistic that the total high-grade
subset will grow and exceed the Company’s target of >30Mt and commensurate growth of the
total MRE >0.5% V2O5 cut-off will likely occur as a by-product of this work.
Drill programmes to test these areas will be investigated by the Company as part of future work
programmes.
7
Viking Mines (ASX:VKA) ASX Announcement 30 November 2022 – Viking to Farm Into Substantial Battery Minerals Project
ASX:VKA | vikingmines.com
3
Figure 2 – Map of the Fold Nose Deposit with 2023 MRE limits shown and target areas for further growth of the MRE
illustrated.
Figure 3 – Map of the Kinks Deposit with 2023 MRE limits shown and target areas for further growth of the MRE
illustrated.
ASX:VKA | vikingmines.com
4
Figure 4 – Map of the Kinks South Deposit with 2023 MRE limits shown and target areas for further growth of the
MRE illustrated.
Metallurgical Testwork
During the quarter, the Company commenced Stage 2 Metallurgical Testwork and engaged
Bureau Veritas to undertake the work. 29 samples obtained from hole VCRC0026 which was
drilled as part of the 7,500m RC drill programme completed mid 2023 were submitted, with
the main zone from the Fold Nose Deposit being evaluated.
A 43.5kg bulk composite sample was created by combining 1.5kg of material from each of the
29 samples provided to the laboratory. 5 x 150g splits of this bulk composite sample
underwent grind establishment tests to determine the optimum grind size. Samples were
ground to different size fractions ranging from 212 to 45µm (P98) and underwent subsequent
Davis Tube Recovery (DTR) testing to produce a magnetic concentrate.
The examination of the magnetic concentrate and tail produced has identified the following
significant attributes, with the detailed findings in Table 3 and Table 4 below:
•
The ore has a low sensitivity to grind size to produce a quality concentrate.
•
Mass recovery remains high, ranging between 52.2% to 54.6%
•
Concentrate grade remains consistent for key target elements, ranging between;
•
•
V2O5: 1.40% to 1.41%
•
Fe: 58.0% to 58.6%
•
TiO2: 11.2% to 11.7%
Combined silica and alumina levels are low (from 4.1% to 4.6%) but will require a further
regrind and cleaning stage to achieve target levels.
ASX:VKA | vikingmines.com
5
Figure 5 – Cross section through hole VCRC0026 from the Fold Nose Deposit showing the samples selected for
metallurgical testwork. The intercept selected for testwork reports 29m at 0.80% V 2O5, 36.6% Fe and 8.8% TiO2 from
138m. Values shown are for V2O5.
Table 3 – Magnetic concentrate results showing mass recoveries, grades and metal recoveries by size fraction.
Table 4 – Tail results showing mass recoveries, grades and metal recoveries by size fraction
ASX:VKA | vikingmines.com
6
Figure 6 – Photos showing A) Samples being prepared for filtration after DTR testwork completed, B) Eirez Davis
Tube tester setup for sighter DTR testing and C) Magnetic concentrate produced after filtration.
FIRST HIT LITHIUM AND GOLD PROJECT
The Company’s First Hit Project (“First Hit Project”) is located 50km west of Menzies in the WA
Goldfields.
During the reporting period, the Company completed a review of the limited historical data
and identified lithium anomalies in soil samples and rock chips on Viking’s wholly owned
tenure.
The most significant anomalies are located on E30/529 with multiple zones >50ppm Li up to
250m wide and 700m long (Figure 7). The orientation of the anomalies suggests that the
potential source of mineralisation may be NW-SE striking, which correlates with the orientation
of pegmatites identified at the First Hit Lithium-Gold Project.
In addition, the Company completed a transaction to acquire 95% of tenement E30/505,
located to the NW of the First Hit mine. The Company has assessed rock chip data with results
up to 400ppm Lithium and corresponding high elevated Rubidium values up to 3,000ppm.
In conjunction with the Lithium values recorded, Rubidium is associated with rare element
pegmatites, providing an indication of the potential of the tenement.
Multiple interpreted pegmatites have been identified in historic literature searches forming a
NW-SE trending swarm across the tenement. An evaluation of the satellite imagery has
revealed a series of NE-SW striking features, which correlate with the historical data (Figure 8).
ASX:VKA | vikingmines.com
7
Figure 7 – Map showing the southern end of Viking tenement E30/529 with the location of historical samples (data
sourced from WAMEX). Strong NW-SE orientated >50ppm Lithium anomalies are evident.
ASX:VKA | vikingmines.com
8
Figure 8 – Map showing the geology, rock chip samples and interpreted pegmatites on tenement E30/505. Note NESW trend of pegmatite swarm and large amount of unsampled pegmatites.
1,200 Hole Auger Programme Completed
To assess this lithium potential of the Mt Ida fault/Zuleika shear corridor covered by Vikings
tenure, a regional auger drilling programme was undertaken. A total of 1,220 holes was
completed for 1,991m across the primary tenement holdings located along the Mt Ida Fault
and encompassing an area of >55km2. The primary objective of the program was to collect
samples for analysis of multiple elements, with a focus on Lithium and Gold.
The auger programme was designed as an initial first phase exploration pass, with sampling
occurring predominantly on a 200m x 400m grid throughout the target area. The goal is to
define geochemical anomalies >50ppm Li across the large portion of tenure never previously
assessed for Lithium. The programme is also aiming to expand the >50ppm Li anomalies
identified in the historical data by infill sampling in the locations shown on Figure 7.
The results will be used to direct the strategy for further follow up field work to identify the
source of the anomalies. All samples have now been delivered to the laboratory for analysis
and assay results are pending. These results will play a crucial role in shaping the direction of
follow-up exploration activities.
ASX:VKA | vikingmines.com
9
Figure 9 – Map showing the completed auger hole locations and historical sample results.
Growing Land Position in a Prolific Lithium District
Viking is actively pursuing prospective tenure around the substantial landholding already
established on the Mt Ida Fault.
As part of this strategy, the Company purchased a 95% interest to all minerals in tenement
E30/505. The tenement is located immediately to the west of Viking’s current tenure and
complements the existing land package.
Further, the Company has pegged additional tenements to the east and west. E30/570 is going
through the approvals process, whilst E30/571 is subject to a ballot with three other parties
and is expected to be held in January 2024. The total land package including applications now
stands at >535km2.
ASX:VKA | vikingmines.com
10
Figure 10 – Location of the First Hit Project tenements and adjoining Company landholdings 8. See Appendix 2 for
details of the Delta Lithium MRE breakdown by resource classification.
Mt Ida MRE is Inferred and Indicated, refer to Delta Lithium (ASX:DLI) ASX Announcement 3 October 2023: Mt Ida Lithium Project Mineral
Resource Estimate upgrade.
8
ASX:VKA | vikingmines.com
11
CORPORATE
Board Appointments
The Company appointed Mr Bevan Tarratt as Non-Executive Director to the Board.
Company Secretary
The Company appointed Ms Michaela Stanton-Cook as Joint Company Secretary.
2023 Annual General meeting
The Company successfully held its annual general meeting of shareholders at 10:00am (WST)
on Wednesday, 22 November 2023 at 15-17 Old Aberdeen Place, West Perth WA 6005,
where all resolutions put to shareholders were approved.
Other
The Company has a strong cash position of $5.1M as of 31 December 2023.
Income for the period totalled $36k from investing activities (bank interest).
The Company’s cash position realised a net decrease of $431k over the December 2023
quarter Appendix 5B cashflow report.
As set out in section 6 of the attached Appendix 5B, the Company made payments to related
parties of the entity of $134k in the quarter ending 31 December 2023. This amount comprised
Director fees for the relevant period.
The Company advises that in accordance with the requirements of ASX Listing Rule 5.3, the
Company’s expenditure on exploration and evaluation activities for the quarter predominantly
related to:
•
$202k: Exploration expenditure on the Canegrass Project to complete the updated Mineral
Resource Estimate and commencement of metallurgical testwork and exploration
expenditure on the First Hit Project related to the completion of the field component of the
Auger drilling programme detailed above.
•
$123k: General corporate and administration costs.
•
$142k: Director fees and staff costs.
•
$58k loss was incurred due to exchange rate variations associated with the cash reserves
held in USD by the Company.
Other than as set out in this report, the Company undertook no other substantive exploration,
mining production and development activities during the quarter.
MARCH QUARTER PLANNED ACTIVITIES
The Company continues to make key advancements at the Canegrass Project and progressing
exploration activities across the First Hit Lithium and Gold Project.
•
Receipt of auger assays from the First Hit Project
•
Ongoing stage 2 Metallurgical Testwork on samples from the Canegrass Project
•
Commence pit optimisation studies on the updated MRE for the Canegrass Project.
ASX:VKA | vikingmines.com
12
Corporate Opportunities
The Company continues to review and conduct due diligence on a vast array of mineral
acquisition opportunities, to compliment the Company’s existing project portfolio, with the
objective of acquiring mature exploration assets with the potential to deliver long-term
shareholder returns. The Board believes the Company is uniquely positioned to capitalise on
some of the opportunity’s that currently exist in the sector and has particular focus on acquiring
advanced future metal projects. The Company will update the market should any of these
opportunities that are being reviewed proceed to a more formal stage in line with the
Company’s continuous disclosure obligations.
END
This announcement has been authorised for release by the Board of the Company.
Julian Woodcock
Managing Director and CEO
Viking Mines Limited
For further information, please contact:
Viking Mines Limited
Sarah Wilson - Company Secretary
+61 8 6245 0870
Competent Persons Statement – Exploration Results
Information in this release that relates to Exploration Target, Exploration Results is based on information compiled by Mr Julian
Woodcock, who is a Member and of the Australian Institute of Mining and Metallurgy (MAusIMM(CP) – 305446). Mr Woodcock is
a full-time employee of Viking Mines Ltd. Mr Woodcock has sufficient experience which is relevant to the style of mineralisation
and type of deposit under consideration and to the activity being undertaken to qualify as a Competent Person as defined in the
2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Mr Woodcock
consents to the disclosure of the information in this report in the form and context in which it appears.
Competent Persons Statement – Mineral Resources
The information in this report that relates to the Mineral Resource estimate is derived from information compiled by Mr Dean
O’Keefe, a Fellow of the Australasian Institute of Mining and Metallurgy (AusIMM, #112948), and Competent Person for this style
of mineralisation. Mr O’Keefe is a consultant to Viking Mines Limited, and is employed by MEC Mining, an independent mining
and exploration consultancy. Mr O’Keefe has sufficient experience relevant to the style of mineralisation and type of deposit under
consideration and to the activity which he is undertaking to qualify as Competent Person as defined in the 2012 edition of the
Australasian Code for the Reporting of Exploration Results, Mineral Resources, and Ore Reserves (JORC Code). Mr O’Keefe
consents to the inclusion in the report of the matters based on the results in the form and context in which they appear. The
Company is not aware of any new information or data that materially affects the information included in the original market
announcements and that all material assumptions and technical parameters underpinning the estimates in the relevant market
announcement continue to apply and have not materially changed. The Company confirms that the form and context in which the
Competent Person’s findings are presented have not been materially modified from the original announcement on 20 November
2023.
Competent Persons Statement – Metallurgical Results
The information contained in this report, relating to metallurgical results, is based on, and fairly and accurately represent the
information and supporting documentation prepared by Mr Damian Connelly. Mr Connelly is a full-time employee of METS
Engineering who are a Contractor to Viking Mines Ltd, and a Fellow of The Australasian Institute of Mining and Metallurgy. Mr
Connelly has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration, and to
the activity being undertaken to qualify as a Competent Person as defined in the 2012 Edition of the Australasian Code for
Reporting of Exploration Results, Exploration Targets, Mineral Resources and Ore Reserves. The Company confirms that the form
and context in which the Competent Person’s findings are presented have not been materially modified from the original market
announcement.
ASX:VKA | vikingmines.com
13
APPENDIX 1 – TENEMENTS HELD OR WITH AN AGREEMENT TO ACQUIRE AN
EQUITY INTEREST AS AT 31 DECEMBER 2023
Australia
Project
License
name
M30/0091
M30/0099
P30/1144
E29/1133
First Hit Project
E30/0529
P29/2652
P30/1137
E29/1131
E29/1169
E30/0570
E30/0571
Location
Western
Australia
Western
Australia
Western
Australia
Western
Australia
Western
Australia
Western
Australia
Western
Australia
Western
Australia
Western
Australia
Western
Australia
Western
Australia
License type
License Holder/ JV
Partners i
Viking Mines
Ownership/
Involvement ii
Mining Licence
Red Dirt Mining Pty Ltd
100%
Mining Licence
Red Dirt Mining Pty Ltd
100%
Red Dirt Mining Pty Ltd
100%
Viking Mines Ltd
100%
Viking Mines Ltd
100%
Viking Mines Ltd
100%
Red Dirt Mining Pty Ltd
100%
Prospecting
Licence
Exploration
Licence
Exploration
Licence
Prospecting
Licence
Prospecting
Licence
Exploration
Licence
Exploration
Licence
Exploration
Licence
Exploration
Licence
Viking Mines Ltd
Red Dirt Mining Pty Ltd
Viking Mines Ltd
Viking Mines Ltd
E30/505
Western
Australia
Exploration
Licence
Viking Mines Ltd
E30/0517
Western
Australia
Exploration
Licence
Baudin Resources Pty Ltd.
100%
(under application)
100%
(under application)
100%
(under application)
100%
(under application)
95%
(pending transfer
by DEMIRS)
0%(option over
exclusive area
over part of the
tenement)
Western
Prospecting
Viking Critical Minerals Pty Ltd
100%
Australia
Licence
Western
Prospecting
P58/1942
Viking Critical Minerals Pty Ltd
100%
Australia
Licence
Western
Prospecting
E58/0604
Viking Critical Minerals Pty Ltd
100%
Australia
Licence
Western
Exploration
Viking Critical Minerals Pty Ltd/
E58/0232
Australia
Licence
Flinders Canegrass Pty Ltd
Western
Exploration
Viking Critical Minerals Pty Ltd/
E58/0236
Australia
Licence
Flinders Canegrass Pty Ltd
25% acquired
Western
Exploration
Viking Critical Minerals Pty Ltd/
E58/0282
(under Farm-In
Australia
Licence
Flinders Canegrass Pty Ltd
arrangement
Western
Exploration
Viking Critical Minerals Pty Ltd/
pending transfer
E58/0520
Australia
Licence
Flinders Canegrass Pty Ltd
by DEMIRS)
Western
Exploration
Viking Critical Minerals Pty Ltd/
E58/0521
Australia
Licence
Flinders Canegrass Pty Ltd
Western
Exploration
Viking Critical Minerals Pty Ltd/
E58/0522
Australia
Licence
Flinders Canegrass Pty Ltd
Western
Exploration
E59/2864
Viking Mines Ltd
100%
Australia
Licence
Western
Exploration
100%
E59/2865
Viking Mines Ltd
Australia
Licence
(under application)
Western
Exploration
E59/2866
Viking Mines Ltd
100%
Australia
Licence
Western
Exploration
E59/2867
Viking Mines Ltd
100%
Australia
Licence
Red Dirt Mining Pty Ltd and Viking Critical Minerals are 100% owned subsidiaries of Viking Mines Ltd.
Granted tenure unless otherwise stated.
Narndee
Project
Canegrass Project
P58/1943
i)
ii)
ASX:VKA | vikingmines.com
14
APPENDIX 2 – DELTA LITHIUM MINERAL RESOURCE
Delta Lithium Limited (ASX:DLI) released an update to the Mt Ida Lithium Mineral Resource
on 3 October 2023. Below is the MRE table for Mt Ida that was released by DLI. For further
information, readers are directed to the ASX Announcement on 3 October 2023 entitled “Mt
Ida Lithium Mineral Resource Estimate Update”:
ASX:VKA | vikingmines.com
15
Rule 5.5
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
VIKING MINES LIMITED
ABN
Quarter ended (“current quarter”)
38 126 200 280
31 DECEMBER 2023
Consolidated statement of cash flows
Current quarter
$A’000
1.
Cash flows from operating activities
1.1
Receipts from customers
1.2
Payments for
(a) exploration & evaluation
Year to date
(6 months)
$A’000
(202)
(1,309)
(d) staff costs
(142)
(252)
(e) administration and corporate costs
(123)
(612)
36
52
(b) development
(c) production
1.3
Dividends received (see note 3)
1.4
Interest received
1.5
Interest and other costs of finance paid
1.6
Income taxes paid
1.7
Government grants and tax incentives
1.8
Other (provide details if material)
1.9
Net cash from / (used in) operating
activities
2.
Cash flows from investing activities
2.1
Payments to acquire or for:
3,310
(431)
1,189
-
(225)
(a) entities
(b) tenements
(c) property, plant and equipment
(d) exploration & evaluation
(e) investments
(f)
other non-current assets
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 1
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Consolidated statement of cash flows
2.2
Current quarter
$A’000
Year to date
(6 months)
$A’000
Proceeds from the disposal of:
(a) entities
(b) tenements
(c) property, plant and equipment
(d) investments
(e) other non-current assets
2.3
Cash flows from loans to other entities
2.4
Dividends received (see note 3)
2.5
Other (provide details if material)
2.6
Net cash from / (used in) investing
activities
3.
Cash flows from financing activities
3.1
Proceeds from issues of equity securities
(excluding convertible debt securities)
3.2
Proceeds from issue of convertible debt
securities
3.3
Proceeds from exercise of options
3.4
Transaction costs related to issues of equity
securities or convertible debt securities
3.5
Proceeds from borrowings
3.6
Repayment of borrowings
3.7
Transaction costs related to loans and
borrowings
3.8
Dividends paid
3.9
Other (provide details if material)
3.10
Net cash from / (used in) financing
activities
4.
Net increase / (decrease) in cash and
cash equivalents for the period
4.1
-
(225)
-
-
Cash and cash equivalents at beginning of
period
5,578
4,132
4.2
Net cash from / (used in) operating
activities (item 1.9 above)
(431)
1,189
4.3
Net cash from / (used in) investing activities
(item 2.6 above)
-
(225)
4.4
Net cash from / (used in) financing activities
(item 3.10 above)
-
-
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
3463-0865-1562, v. 1
Page 2
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Consolidated statement of cash flows
Current quarter
$A’000
Year to date
(6 months)
$A’000
4.5
Effect of movement in exchange rates on
cash held
(58)
(7)
4.6
Cash and cash equivalents at end of
period
5,089
5,089
5.
Reconciliation of cash and cash
equivalents
Current quarter
$A’000
Previous quarter
$A’000
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
5.1
Bank balances
5,089
5,578
5.2
Call deposits
5.3
Bank overdrafts
5.4
Other (provide details)
5.5
Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
5,089
5,578
6.
Payments to related parties of the entity and their
associates
6.1
Aggregate amount of payments to related parties and their
associates included in item 1
134
6.2
Aggregate amount of payments to related parties and their
associates included in item 2
-
Current quarter
$A'000
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and an
explanation for, such payments.
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
3463-0865-1562, v. 1
Page 3
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
7.
Financing facilities
Note: the term “facility’ includes all forms of financing
arrangements available to the entity.
Add notes as necessary for an understanding of the
sources of finance available to the entity.
Total facility
amount at quarter
end
$A’000
Amount drawn at
quarter end
$A’000
7.1
Loan facilities
7.2
Credit standby arrangements
7.3
Other (please specify)
7.4
Total financing facilities
7.5
Unused financing facilities available at quarter end
7.6
Include in the box below a description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any additional financing
facilities have been entered into or are proposed to be entered into after quarter end,
include a note providing details of those facilities as well.
8.
Estimated cash available for future operating activities
8.1
Net cash from / (used in) operating activities (item 1.9)
8.2
(Payments for exploration & evaluation classified as investing
activities) (item 2.1(d))
8.3
Total relevant outgoings (item 8.1 + item 8.2)
(431)
8.4
Cash and cash equivalents at quarter end (item 4.6)
5,089
8.5
Unused finance facilities available at quarter end (item 7.5)
8.6
Total available funding (item 8.4 + item 8.5)
8.7
Estimated quarters of funding available (item 8.6 divided by
item 8.3)
$A’000
(431)
-
5,089
11.81
Note: if the entity has reported positive relevant outgoings (ie a net cash inflow) in item 8.3, answer item 8.7 as “N/A”.
Otherwise, a figure for the estimated quarters of funding available must be included in item 8.7.
8.8
If item 8.7 is less than 2 quarters, please provide answers to the following questions:
8.8.1
Does the entity expect that it will continue to have the current level of net operating
cash flows for the time being and, if not, why not?
Answer: N/A
8.8.2
Has the entity taken any steps, or does it propose to take any steps, to raise further
cash to fund its operations and, if so, what are those steps and how likely does it
believe that they will be successful?
Answer: N/A
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
3463-0865-1562, v. 1
Page 4
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
8.8.3
Does the entity expect to be able to continue its operations and to meet its business
objectives and, if so, on what basis?
Answer:
Note: where item 8.7 is less than 2 quarters, all of questions 8.8.1, 8.8.2 and 8.8.3 above must be answered.
Compliance statement
1
This statement has been prepared in accordance with accounting standards and policies which
comply with Listing Rule 19.11A.
2
This statement gives a true and fair view of the matters disclosed.
Date:
...................................................................................
Authorised by: ...................................................................................
(Name of body or officer authorising release – see note 4)
Notes
1.
This quarterly cash flow report and the accompanying activity report provide a basis for informing the market about the
entity’s activities for the past quarte