VKA PARTNERS WITH WSP TO FAST-TRACK LINKA PERMITTING
Released
Released
Announcement PDF
contact@vikingmines.com
1
ASX ANNOUNCEMENT
19 March 2026
15-17 Old Aberdeen Place
West Perth, WA, 6005
P +61 8 6245 0870
F +61 8 9322 5230
ASX:VKA
vikingmines.com
VIKING PARTNERS WITH GLOBAL CONSULTANCY WSP TO
FAST-TRACK LINKA PERMITTING
• WSP USA Inc. (WSP) engaged for permitting support and data acquisition, effectively
compressing the Project development timeline.
• Tier-1 global consultancy WSP provides ~83,000 employees and a significant local
presence in the Nevada mining sector.
• Immediate commencement of baseline studies forms a core component of Viking’s
fast-track strategy to de-risk the Project.
• Integrated approach ensures permitting workstreams run in parallel with ongoing
metallurgical, engineering, and geological programmes.
• Surveys initiated to capture critical biological and water data, securing a proprietary
database and enhancing asset value.
Viking Mines Ltd (ASX: VKA) (“Viking” or “the Company”) is pleased to report the
engagement of global professional services firm WSP USA Inc. (a subsidiary of WSP Global Inc.)
to support Viking along the permitting pathway and commence critical baseline data acquisition
at the Linka Tungsten Project in Nevada, USA.
Viking Mines MD & CEO Julian Woodcock said:
"Engaging WSP is another critical step in moving Linka toward a development-ready state. By
commencing the permitting process with baseline data collection an in parallel with
metallurgical, engineering and geological programmes, we are effectively compressing the
development timeline.
"Building this proprietary database today de-risks the asset and ensures we are well advanced
on the pathway towards future permitting."
ACCELERATING PERMITTING PATHWAY
The Company has secured WSP USA Inc. (“WSP”) to manage baseline studies and develop a
permitting strategy for the Linka Project. WSP is a premier global engineering firm with 83,000
employees and deep expertise within the Nevada mining industry. This strategic partnership
ensures that Viking has access to world-class technical resources and established regulatory
relationships within the United States.
This proactive engagement is central to Viking’s fast-track strategy. Capturing time-sensitive
data early in the Project life cycle streamlines the transition toward advanced exploration and
potential future development. By integrating these requirements into the current technical
workflow, the Company is taking a holistic approach to project management that prioritises
efficiency and risk mitigation.
ASX:VKA | vikingmines.com 2
PERMITTING PATHWAY AND DATA ACQUISITION
WSP are completing a work programme that is structured into three primary phases to move
Linka toward development readiness in parallel with other technical workstreams:
• Phase 1 – Baseline Data and Strategy: Initiation of desktop and terrestrial assessments to
establish a comprehensive project foundation. This phase defines the optimal permitting
roadmap and identifies critical statutory and regulatory milestones for future operations.
• Phase 2 – Resource Characterisation: A comprehensive field programme of biological,
water resource, and cultural surveys to capture necessary field data. These surveys are
essential for building a detailed profile of the Project area to meet state and federal
requirements.
• Phase 3 – Regulatory Compliance: Facilitation of documentation and site assessments
required for the authorisation of advanced exploration or development plans. This phase
involves direct coordination with regulatory bodies to ensure all compliance benchmarks
are met seamlessly.
STRATEGIC RATIONALE: BUILDING AN ADVANCED ASSET
Initiating these studies represents a critical milestone in the Project's evolution. By running this
work in parallel with Mineral Technologies processing concept design1
and the Viking managed
geological exploration programme, the Company is effectively compressing the overall
development timeline. This concurrent processing avoids the common industry pitfall of
sequential development, where permitting only begins after technical studies are complete.
Furthermore, acquiring baseline data builds a high-value proprietary database. This de-risks the
Project and accelerates its transition to development-ready status, significantly increasing asset
valuation for all stakeholders. A Project with a matured permitting profile is inherently more
attractive and valuable than one at the purely conceptual stage.
This systematic approach ensures the Company remains compliant with Federally managed
lands and state requirements, while maintaining the momentum required to bring the Linka
Project into development as rapidly as possible.
NEXT STEPS
With the engagement of WSP, the Company has commenced the necessary works to ensure
baseline data is collected which will be required for future compliance and permitting. Key next
steps associated with WSP include:
• Initial Surveys: Commencement of terrestrial and desktop assessments.
• Strategy Finalisation: Completion of the permitting roadmap to define the pathway for
future operations.
• Resource Surveys: Deployment of field teams for biological and water resource
monitoring.
END
1
VKA ASX Announcement, 17 March 2026 - VKA Engages Mineral Technologies for Linka Tungsten
ASX:VKA | vikingmines.com 3
This announcement has been authorised for release by the Board of the Company.
Julian Woodcock
Managing Director and CEO
Viking Mines Limited
For further information, please contact:
Viking Mines Limited
Michaela Stanton-Cook - Company Secretary
+61 8 6245 0870
Forward-Looking Statements
This document may include forward-looking statements. Forward-looking statements include, but are not limited to, statements
concerning Viking Mines Limited’s planned exploration programme and other statements that are not historical facts. When used in
this document, the words such as "could," "plan," "estimate," "expect," "intend," "may”, "potential," "should," and similar expressions
are forward-looking statements. Although Viking Mines Limited believes that its expectations reflected in these forward-looking
statements are reasonable, such statements involve risks and uncertainties and no assurance can be given that actual results will be
consistent with these forward-looking statement.
Competent Persons Statement – Exploration Results
Information in this release that relates to Exploration Results is based on information compiled by Mr Julian Woodcock, who is a
Member of the Australian Institute of Mining and Metallurgy (MAusIMM(CP) – 305446). Mr Woodcock is a full-time employee of
Viking Mines Ltd. Mr Woodcock has sufficient experience which is relevant to the style of mineralisation and type of deposit under
consideration and to the activity being undertaken to qualify as a Competent Person as defined in the 2012 Edition of the
‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Mr Woodcock consents to the
disclosure of the information in this report in the form and context in which it appears. The Company confirms that it is not aware of
any new information or data that materially affects the information included in the original announcements and that all material
assumptions and technical parameters underpinning the Exploration Results in the original announcements continue to apply and
have not materially changed. The Company confirms that the form and context in which the Competent Person’s findings are
presented have not been materially modified from the original announcements.