VIKING COMPLETES AUGER DRILLING AT FIRST HIT
LITHIUM & GOLD PROJECT
•
Viking Mines has completed the auger drilling programme and collected 1,220
samples at the First Hit Lithium & Gold Project.
•
Sampling has been completed over a 26km strike length of the Ida Fault and tests
>55km2 of highly prospective tenure.
•
Samples have been dispatched to lab for analysis, with results expected in January
2024.
•
The programme is focussed on assessing the lithium and gold potential of the Project
which sits along strike of Delta Lithium’s Mount Ida Lithium Gold Project.
•
Multiple >50ppm Lithium anomalies identified in historic data on Viking tenure, up
to 200m x 700m, which had seen no follow up activity until now.1
Viking Mines Limited (ASX: VKA) (“Viking” or “the Company”) is pleased to provide an
update on exploration activities at the Company’s First Hit Lithium & Gold Project (“the Project”
or “First Hit”), located west of Menzies in the Western Australia Goldfields.
The Company has completed the collection of 1,220 samples along a 26km strike length of the
Ida Fault, encompassing >55km2 of highly prospective tenure.
The Project is situated 60km south and along strike of Delta Lithium’s Mount Ida Lithium Gold
Project, that has delineated a substantial Mineral Resource Estimate totalling 14.6Mt at 1.2%
Li2O.2
Viking’s granted tenure in this district now stands at ~291km2, with additional tenement
applications in process bringing the total land package >535km2.
Viking Mines Managing Director & CEO Julian Woodcock said:
“The Company has successfully completed a major auger drilling and sampling programme,
which has been designed as a first pass to assess the lithium and gold potential of the Project.
“The First Hit Lithium and Gold Project is located on the Ida Fault, which is highly prospective
for Lithium and is directly south and along strike of the Delta Lithium Mt Ida Project.
“The focus of the programme is to both follow up historical lithium anomalies identified by the
Company at the southern end of the tenure, as well as significantly expand the dataset across
an extensive 26km strike length of this highly prospective region, with the areas of focus never
previously been tested for Lithium.
“I am excited by the prospects of what we might find with the results given the extensive number
of pegmatites seen in the district and look forward to updating the market with the results of this
program early next year.”
1
ASX Announcement Viking Mines (ASX: VKA) 27 November 2023 – VKA Grows Tenure & Starts Lithium Exploration at First Hit
Mt Ida MRE is Inferred and Indicated, refer to Delta Lithium (ASX:DLI) ASX Announcement 3 October 2023: Mt Ida Lithium
Project Mineral Resource Estimate upgrade. Breakdown of classification at the end of this announcement in Note 1.
2
ASX:VKA
vikingmines.com
15-17 Old Aberdeen Place
West Perth, WA, 6005
P +61 8 6245 0870
F +61 8 9322 5230
contact@vikingmines.com
1
1,220 HOLE AUGER PROGRAMME COMPLETED
Auger drilling operations have been completed at the First Hit Project (Figure 1).
A total of 1,220 holes have been completed for 1,991m across the primary tenement holdings
located along the Mt Ida Fault and encompassing an area of >55km2. The primary objective of
the program was to collect samples for analysis of multiple elements, with a focus on Lithium
and Gold.
The auger programme has been designed as an initial first phase exploration pass, with
sampling occurring predominantly on a 200m x 400m grid throughout the target area
(Figure 2). The goal is to define geochemical anomalies >50ppm Li across the large portion of
tenure never previously assessed for Lithium. The programme is also aiming to expand the
>50ppm Li anomalies identified in the historical data by infill sampling in the locations shown
on Figure 1.
The results will be used to direct the strategy for further follow up field work to identify the
source of the anomalies.
All samples have now been delivered to the laboratory for analysis and assay results are
anticipated to be received in January. These results will play a crucial role in shaping the
direction of follow-up exploration activities.
Figure 1; Gyro Australia Auger drill rig drilling at the First Hit Gold & Lithium Project and soil anomalies in the southern part of the
tenure with infill sample locations shown.1
ASX:VKA | vikingmines.com
2
Figure 2; Map showing the completed auger hole locations and historical sample results.
ASX:VKA | vikingmines.com
3
NEXT STEPS
Viking is progressing exploration at the First Hit Lithium & Gold Project with the objective of
identifying high-quality targets for follow up exploration activity that have the potential to
deliver economic deposits for Lithium or Gold.
•
Obtain assay data from the laboratory, estimated to be received in January 2024.
•
Engagement of specialist consultants to evaluate analysis results to assess the fertility
potential of the areas sampled for LCT type pegmatites.
•
Define geochemical anomalies with a focus on areas >50ppm Lithium for field
investigation and follow up.
•
Asses anomalous areas for infill soil and/or auger sampling.
•
Undertake field mapping of anomalous areas to identify potential sources of the
anomalies and collect geological data and rock chip samples to guide planning of follow
up drilling programmes.
END
This announcement has been authorised for release by the Board of the Company.
Julian Woodcock
Managing Director and CEO
Viking Mines Limited
ASX:VKA | vikingmines.com
For further information, please contact:
Viking Mines Limited
Sarah Wilson - Company Secretary
+61 8 6245 0870
4
Forward-Looking Statements
This document may include forward-looking statements. Forward-looking statements include, but are not limited to, statements
concerning Viking Mines Limited’s planned exploration programme and other statements that are not historical facts. When
used in this document, the words such as "could," "plan," "estimate," "expect," "intend," "may”, "potential," "should," and similar
expressions are forward-looking statements. Although Viking Mines Limited believes that its expectations reflected in these
forward-looking statements are reasonable, such statements involve risks and uncertainties and no assurance can be given that
actual results will be consistent with these forward-looking statements.
Competent Persons Statement – Exploration Results
Information in this release that relates to Exploration Results is based on information compiled by Mr Julian Woodcock, who is
a Member and of the Australian Institute of Mining and Metallurgy (MAusIMM(CP) – 305446). Mr Woodcock is a full-time
employee of Viking Mines Ltd. Mr Woodcock has sufficient experience which is relevant to the style of mineralisation and type
of deposit under consideration and to the activity being undertaken to qualify as a Competent Person as defined in the 2012
Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Mr Woodcock
consents to the disclosure of the information in this report in the form and context in which it appears.
Competent Persons Statement – Mineral Resource Estimate
The information in this announcement that relates to the Canegrass Battery Minerals Project Mineral Resource Estimate is
derived from information compiled by Mr Dean O’Keefe, a Fellow of the Australasian Institute of Mining and Metallurgy
(AusIMM, #112948), and Competent Person for this style of mineralisation. Mr O’Keefe is a consultant to Viking Mines Limited,
and is employed by MEC Mining, an independent mining and exploration consultancy. Mr O’Keefe has sufficient experience
relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to
qualify as Competent Person as defined in the 2012 edition of the Australasian Code for the Reporting of Exploration Results,
Mineral Resources, and Ore Reserves (JORC Code). The Company confirms that the form and context in which the results are
presented and all material assumptions and technical parameters underpinning the estimates in the original market
announcement continue to apply and have not materially changed from the original announcement and that the form and
context in which the Competent Person’s findings are presented have not been materially modified from the original
announcement on 20 November 2023.
NOTE 1 – DELTA LITHIUM MINERAL RESOURCE
Delta Lithium Limited (ASX:DLI) released an update to the Mt Ida Lithium Mineral Resource
on 3 October 2023. Below is the MRE table for Mt Ida that was released by DLI. For further
information, readers are directed to the ASX Announcement on 3 October 2023 entitled “Mt
Ida Lithium Mineral Resource Estimate Update”:
ASX:VKA | vikingmines.com
5
FIRST HIT LITHIUM GOLD PROJECT
The Project is situated 60km south and along strike of Delta Lithium’s Mount Ida Lithium Gold
Project, that has delineated a substantial Mineral Resource Estimate totalling 14.6Mt at 1.2%
Li2O. Viking’s land package of granted tenements now stands at ~291km2.
Viking is actively pursuing prospective tenure around the substantial landholding already
established on the Mt Ida Fault. As part of this strategy, the Company has purchased a 95%
interest to all minerals in tenement E30/505. The tenement is located immediately to the west
of Viking’s current tenure and complements the existing land package.
Further, the Company has pegged additional tenements to the east and west. E30/570 is going
through the approvals process whilst E30/571 is subject to a ballot with three other parties, the
date of which is yet to be announced by the Western Australian government. The total land
package including applications stands at >535km2 (including 291km2 granted).
Figure 3; Location of the First Hit Project tenements and adjoining Company landholdings.
ASX:VKA | vikingmines.com
6
ADDITIONAL VIKING PROJECTS: CANEGRASS BATTERY MINERALS PROJECT
The Canegrass Battery Minerals Project is located in the Murchison region, 620km north-east
of Perth, Western Australia. It is accessed via sealed roads from the nearby township of Mt
Magnet to within 22km of the existing Resources. The Project benefits from a large
undeveloped Inferred Vanadium Resource hosted in vanadiferous titanomagnetite (VTM)
Mineralisation as part of the Windimurra Layered Igneous Complex.
The Project benefits from ~95km2 of exploration tenements with very limited follow up
exploration targeting the growth potential of the vanadium pentoxide (V2O5) Resources in the
+10 years since the Resource was first calculated and prior to Vikings involvement.
Viking has completed substantial exploration activity since acquiring the Project which has
culminated in a substantial Mineral Resource Estimate upgrade, doubling the amount of
contained V2O5. The Company is progressing with further metallurgical testwork and studies
with the objective of completing a scoping study in 2024 to determine the potential economics
of the Project.
JORC (2012) MINERAL RESOURCE
The Canegrass Mineral Resource has been calculated across three separate areas called the
Fold Nose, Kinks and Kinks South deposits. The Resource has subsequently been reported
above a cut-off grade of 0.5% V2O5 and above the 210 RL (equivalent to a maximum depth of
~250m)(refer to ASX Announcement on 20 November 2023).
Canegrass Project Vanadium Mineral Resource estimate, 0.5% V 2O5 cut-off grade, >210m RL.
Target Commodities
Deleterious Elements
JORC (2012) Cut-Off Tonnage
Ni
Co Al2O3 SiO2
P
V2O5 Fe TiO2 Cu
Classification V2O5%
(Mt)
%
%
%
%
%
%
%
%
%
VKA 2023 Model
Inferred
>0.5
146
0.70 31.8 6.6 0.066 0.062 0.016 11.7 21.7 0.005
MRE
LOI
%
1.7
VIKING MINES FARM-IN AGREEMENT
Viking, via its wholly owned subsidiary, Viking Critical Minerals Pty Ltd, commenced with a
Farm-In arrangement with Flinders Mines Ltd (ASX:FMS) on 28 November 2022 to acquire an
equity interest in the Canegrass Battery Minerals Project. Through the terms of the Farm-In,
Viking can acquire up to 99% of the Project through completion of 4 stages via a combination
of exploration expenditure of $4M and staged payments totalling $1.25M over a maximum
period of 54 months. As of August 2024, Viking has acquired 25% of the Project through the
FIA.
If Viking progresses the Farm-In to 99% equity interest, Flinders may offer to sell to Viking the
remaining 1% of the Project for future production and milestone related payments totalling
$850,000. If Flinders do not offer to sell within a prescribed timeframe their right lapses, they
must offer Viking the right (but not the obligation) to buy the remaining 1% for the same terms.
The Project has a legacy 2% Net Smelter Royalty over the project from when Flinders Mines
acquired it from Maximus Resources in 2009.
ASX:VKA | vikingmines.com
7
VANADIUM REDOX FLOW BATTERIES – GREEN ENERGY FUTURE
Viking Mines recognise the significant importance of Vanadium in decarbonisation through the
growth of the Vanadium Redox Flow Battery (“VRFB’s”) sector.
VRFB’s are a developing market as an alternate solution to lithium-ion (“Li-ion”) in specific large
energy storage applications. Guidehouse Insights Market Intelligence White Paperi published
in 2Q 2022 forecasts the VRFB sector to grow >900% by 2031 through the installation of large,
fixed storage facilities (Figure 4).
Figure 4; Forecast growth of the VRFB Sector through to 2031 (source – Guidehouse Insightsi)
The reason for this forecast growth is that VRFB’s have unique qualities and advantages over
Li-ion in the large energy storage sector to complement renewable energy sources to store the
energy produced. They are durable, maintain a long lifespan with near unlimited
charge/discharge cycles, have low operating costs, safe operation (no fire risk) and have a low
environmental impact in both manufacturing and recycling. The Vanadium electrolyte used in
these batteries is fully recyclable at the end of the battery’s life.
Importantly, and unlike Li-ion, the battery storage capacity is only limited by the size of the
electrolyte storage tanks. This means that with a VRFB installation, increasing energy storage
capacity is only a matter of adding in additional electrolyte (via the installation of additional
electrolyte storage tanks) without needing to expand the core system components. Increasing
the energy storage directly reduces the levelized cost per kWh over the installation’s lifetime.
This is not an option with Li-ion batteries.
It is for these reasons that VRFB’s are an ideal fit for many storage applications requiring longer
duration discharge and more than 20 years of operation with minimal maintenance.
i) Guidehouse Insights White Paper Vanadium redox Flow Batteries Identifying Market Opportunities and Enablers Published 2Q 2022
https://vanitec.org/images/uploads/Guidehouse_Insights-Vanadium_Redox_Flow_Batteries.pdf
ASX:VKA | vikingmines.com
8
Share your feedback
Discover